Suspended Ceiling Repair

Case Study: 18075

Value
£5,000

Location
ITU (Intensive Treatment Unit), Wexham Park Hospital

Contract Length
5 days

Types of Work Involved:

Emergency suspended ceiling remedial works

The Task:

Repair of partially collapsed suspended ceiling. The Trust commissioned us to find a solution to this emergency remedial works so we could programme and control the works in order for the ITU ward to carry on with its duty of care to their patients. The building task here was straightforward, but the control and preparation was the key to a successful job and a satisfied client.

The Problem:

ITU is a unit for the chronically sick and therefore cannot be closed to carry out the works. It contains very sensitive equipment that cannot be exposed to dust and vibration. The ceiling was in danger of collapse so there was genuine risk to safety of patients, staff and visitors.

The Solution:

After consultations with the Matron, it was decided to move one patient immediately and a plan of works was compiled.

The work had to be carried out promptly so as not to affect the wards capability to serve any incoming sick patients, so getting the ward back up to full capacity was paramount.

Once the plan was agreed, after consultations with the IPC (Infection Prevention Control) team, the Trust’s Estates director and the ward Matron, work commenced immediately.

Firstly, the area was cordoned off with clean hazard barriers that were cleaned prior to placement in the ward with Klericide 70/30 ethanol solution.

10no. 3m x 1200mm screens were assembled and covered in Safelex and screwed together in the ward. Then we used lighter grade polythene from the top of the screens to the top of the vaulted ceilings. All edges were taped with gaffer tape to seal. A change area was constructed to enable safe ingress and egress into the working area. Tack mats were positioned as an added control measure.

All these control/ enabling works were carried out methodically and quietly for minimum disturbance reasons.

Before the remedial works were carried out we contacted the IPC team to inspect and for their approval. The IPC team took some photos of our control measures to show other contractors how they would like all works to be carried out within live wards.

The ceiling was then carefully disassembled and then rebuilt with additional hangers to prevent any further occurrences.

After client and end user inspection. The hospital deep cleaned the working area. We then disassembled the screening in a controlled manner and the bed spaces were then handed back to the ward.

Latest Work

Take a look at some of our most recent work.

Office Extension in Warehouse Area

Construction

Thorpe Park, Bar 360 Refurbishment Works

Leisure

Replacement of Resin Floor in Production Area

Food Manufacturing

Re-siting gas tank storage bases and compound

Pharmaceutical

New Car Parking Area

Manufacturing

Kitchen & Dining Room Floor Remedial

Domestic

Amenities Refurbishment in Factory

Food Manufacturing

Toilet Floor Refurbishment

Education

Replacement of Existing Factory Floor

Food Manufacturing

Factory Epoxy Resin Floor

Food Manufacturing

Sikalastic Roof Cladding Repair

Aviation

Sikalastic Low Level Roof Refurb

Health

Sika Trocal Roof Membrane Install

Retail

Belzona Roof Waterproofing

Estates

Single Ply Flat Roof

Food Manufacturing

Sikalastic Roof Refurbishment

Health

Belzona Leaded Roof Refurbishment

Estates

Belzona Flat Roof, Gutter and Porch Refurb

Estates

Single Storey Office Roof Works

Health

Factory Machine Base Refurbishment

Food Manufacturing

Suspended Ceiling Repair

Health

Disabled Access Wet Room

Health

Porta Cabin Wet Room

Health

HBN Compliant Shower Rooms

Health

Town Hall Refurbishment

Government

Tottenham Hotspur Advertising Boards

Leisure

Tiling of Room and Stairs

Utilities

Telecommunications Installation

Data Centre & IT

School Maintenance and Refurbishment

Education

School Classroom and Toilets Renovation

Education

School Classroom and Entrance Renovation

Education

Roof Decking Refurbishment

Estates

Retaining Wall Install

Domestic

Residential House Renovation

Domestic

Residential Hard Landscaping

Domestic

Residential Flood Damage Refurbishment

Domestic

Newport Church Refurbishment

Heritage

Manchester United Advertising Boards

Leisure

Male & Female Toilets & Family Room Refurbishment

Retail

Lorry Park Resurfacing Works

Logistics

Locker Room and Welfare Facilities Install

Utilities

GB Rowing Team Cabin

Leisure

Gas Storage Compound

Pharmaceutical

Factory Extension

Food Manufacturing

Cricket Club House Refurb

Leisure

Concrete Block Wall

Utilities

Coating of Concrete Bund Walls

Construction

Cladding to Rear Shed

Construction

Battersea Church Refurbishment

Heritage

Wet Room Conversion

Health

Get in touch

If you are interested in receiving further information or would like a quote please fill in the following form:

[salesforce form=”1″]

The Benefits of Using Adamson Construction

We have 25 years of success within the construction industry

We have a clear focus on loyalty, trust and aftercare - our customers appreciate our honesty

One point of contact

We pride ourselves on customer care and go the extra mile

Act as an integrated part of your team – not just your contractor

Not only do we fulfil your immediate requirements, but we oversee and manage your nominated suppliers where necessary

We look at both the short term goals and long term value of all projects

Deliver swift response times with regular communication

Specialists in several industries where our experience and knowledge of these mean we are adaptable to various disciplines, fulfilling our customers’ needs

Understand your unique needs, challenges and goals

Provide a fresh thinking, proactive and enthusiastic approach – helping you save time and money

Accreditations: Achilles, Constructionline, Safecontractor, CHAS, ISO 9001, Investors in People, CORC, FeRFA, FMB

Accreditations

Adamson Construction are proud to be accredited with the following:

TESTIMONIALS

I have dealt with Adamson Construction since 2005, during which time they have provided construction services to the business that I work for. They have demonstrated excellent support in the areas of project management, site safety (CDM) and have provided professional and knowledgeable personnel. Their work has been a factor in ensuring that our projects are completed to budget and schedule.

I can confidently recommend Adamson Construction as a solid and reliable supplier, and experts in their field.

Capital Projects Manager - Pharmaceutical manufacturer, Slough.

Social Media

FOLLOW US ON...