Re-siting gas tank storage bases and compound

Case Study: 17823

Value
£140,000

Location
Bath Road, Slough

Contract Length
3 months

Types of Work Involved:

Civil Engineering / Demolition / Fencing / Brickwork / Structural Engineering / Cladding / Flooring / Plumbing / Painting & Decorating

The Task:

The client was moving premises a short distance and had external plant which required moving as well as new services which required connection. The works incorporated the installation of new a gas compound, pipe bridge, perimeter fencing, and bock paving.

The works were to be designed and installed in line with client specification and approval.

The existing two large gas tanks in a fenced off compound were situated in the car park of the old premises and these had to be re-sited to the new premises.

The Problem:

Due to the site being a live production site the works had to take place while the clients personnel were onsite and in several phases so not to impact production. Works were programmed to the client’s wishes and planned accordingly.

The position of the gas tanks was a good distance from the service exit point of the building. Once the tanks and adjacent temporary buildings had been removed, the walling and floor had to be tidied and made attractive and useable. A new perimeter fence was also required to maintain security. The works had to be carried out giving the clients staff safe access into the building by Youngman boarding over rough terrain from fence line to plantroom doors.

The new base had to be installed with new tanks and piped system all commissioned and filled before existing system could be isolated and drained off. This would ensure no impact on product processing. The base had to be broken with minimal vibration due to a very sensitive plantroom adjacent.

The Solution:

The first phase was to excavate and form the new base foundation for the new gas storage tanks. The bases were designed and calculated for the intended use and installed to specification. Once completed the client arranged to have the Gas storage vessels installed. The next phase was the fabrication and installation of the new pipe bridge. The pipe bridge was fabricated off site and installed onsite. Excavations were made with pre-calculated load bearing concrete bases installed and the columns were bolted into the bases. The bridge was then assembled and painted with metallic oil based paint. Whilst the gas pipework was installed and commissioned, we installed the perimeter fence. All fencing was of a prison mesh construction and powder coated to match pipe bridge. Cladding was then installed to the outside of the pipe bridge at the client’s landlords request to shield the pipe work and pipe bridge from general view. Once all the pipework had been signed off we then installed Uni-Strut to the bridge and prison mesh to protect all pipe work. The third phase was the removal of temporary packing building and timber link to the production building. This work was tied in with the clients programme to meet the exact timeline of the completion of their new packing department, so the old building had to be demolished in a weekend so as not to affect their production. The portable cabin was carefully disengaged from the temporary timber link building and moved to one of the clients other sites where we could carry out a dilapidation of it, in readiness for it to be returned to the supplier. The link building was carefully removed from the production building and disposed of. This work involved isolation and removal of electrical and fire alarm services and demolition of structure along with making good of brickwork and fascia’s to the production building. The fourth and final phase incorporated civil engineering works including demolition of existing gas storage tank, compound fencing and base foundation. The solution for reducing vibration when removing the base was done by cutting the slab into many smaller pieces then lifting out into an adjacent skip. Large amounts of spoil had to be removed and all waste was recycled. This phase included the installation of several hundred square metres of block paved surfaces to North and Western perimeter and the installation of the perimeter prison mesh fencing to define the boundary of the clients land. This phase was problematic for various reasons and had to be planned in a way to not compromise any of the fire escape routes. The finished job gives a pleasing finish throughout. Practical, easy to use, safe and secure.

Latest Work

Take a look at some of our most recent work.

Ascot Single Storey Extension

Residential

Bishopsgate School Extension

Education

Office Extension in Warehouse Area

Construction

Thorpe Park, Bar 360 Refurbishment Works

Leisure

Replacement of Resin Floor in Production Area

Food Manufacturing

Re-siting gas tank storage bases and compound

Pharmaceutical

New Car Parking Area

Manufacturing

Amenities Refurbishment in Factory

Food Manufacturing

Toilet Floor Refurbishment

Education

Replacement of Existing Factory Floor

Food Manufacturing

Factory Epoxy Resin Floor

Food Manufacturing

Sikalastic Roof Cladding Repair

Aviation

Sikalastic Low Level Roof Refurb

Health

Sika Trocal Roof Membrane Install

Retail

Belzona Roof Waterproofing

Estates

Single Ply Flat Roof

Food Manufacturing

Sikalastic Roof Refurbishment

Health

Belzona Leaded Roof Refurbishment

Estates

Belzona Flat Roof, Gutter and Porch Refurb

Estates

Single Storey Office Roof Works

Health

Factory Machine Base Refurbishment

Food Manufacturing

Suspended Ceiling Repair

Health

Disabled Access Wet Room

Health

Portable Cabin Wet Room

Health

HBN Compliant Shower Rooms

Health

Town Hall Refurbishment

Government

Tottenham Hotspur Advertising Boards

Leisure

Tiling of Room and Stairs

Utilities

Telecommunications Installation

Data Centre & IT

School Maintenance and Refurbishment

Education

School Classroom and Toilets Renovation

Education

School Classroom and Entrance Renovation

Education

Roof Decking Refurbishment

Estates

Retaining Wall Install

Residential

Residential House Renovation

Residential

Residential Hard Landscaping

Residential

Residential Flood Damage Refurbishment

Residential

Newport Church Refurbishment

Heritage

Manchester United Advertising Boards

Leisure

Male & Female Toilets & Family Room Refurbishment

Retail

Lorry Park Resurfacing Works

Logistics

Locker Room and Welfare Facilities Install

Utilities

GB Rowing Team Cabin

Leisure

Gas Storage Compound

Pharmaceutical

Factory Extension

Food Manufacturing

Cricket Club House Refurb

Leisure

Concrete Block Wall

Utilities

Coating of Concrete Bund Walls

Construction

Cladding to Rear Shed

Construction

Battersea Church Refurbishment

Heritage

Wet Room Conversion

Health

Kitchen & Dining Room Floor Remedial

Residential

Get in touch

If you are interested in receiving further information or would like a quote please fill in the following form:

[salesforce form=”1″]

The Benefits of Using Adamson Construction

We have 25 years of success within the construction industry

We have a clear focus on loyalty, trust and aftercare - our customers appreciate our honesty

One point of contact

We pride ourselves on customer care and go the extra mile

Act as an integrated part of your team – not just your contractor

Not only do we fulfil your immediate requirements, but we oversee and manage your nominated suppliers where necessary

We look at both the short term goals and long term value of all projects

Deliver swift response times with regular communication

Specialists in several industries where our experience and knowledge of these mean we are adaptable to various disciplines, fulfilling our customers’ needs

Understand your unique needs, challenges and goals

Provide a fresh thinking, proactive and enthusiastic approach – helping you save time and money

Accreditations: Achilles, Constructionline, Safecontractor, CHAS, ISO 9001, Investors in People, CORC, FeRFA, FMB

Accreditations

Adamson Construction are proud to be accredited with the following:

TESTIMONIALS

I have dealt with Adamson Construction since 2005, during which time they have provided construction services to the business that I work for. They have demonstrated excellent support in the areas of project management, site safety (CDM) and have provided professional and knowledgeable personnel. Their work has been a factor in ensuring that our projects are completed to budget and schedule.

I can confidently recommend Adamson Construction as a solid and reliable supplier, and experts in their field.

Capital Projects Manager - Pharmaceutical manufacturer, Slough.

Social Media

FOLLOW US ON...